WhatsApp Icon

Uluwatu's South Ring Road (JLS): Route, Timeline and What It Could Mean for Property Buyers

Aerial view of the South Ring Road corridor on the Bukit Peninsula: a wide cleared white road bed curving through dry bushland and houses, under a blue sky

Introduction

If you have driven the Bukit Peninsula in high season, you know the problem: one main artery, Jalan Raya Uluwatu, carrying residents, tourists, delivery trucks and construction traffic. In 2026 the Badung Regency Government started building a long-discussed answer: the South Ring Road, known locally as Jalan Lingkar Selatan (JLS). This guide covers what has been officially announced, what is still uncertain and what it means if you are looking at property in Uluwatu or Pecatu.

Facts were checked on 19 November 2026 and are dated in the Sources. For the wider buying process, read our complete buying guide.

Key Takeaways

  • Key point: construction of JLS Segment 4 (Labuan Sait to Pedati) started on 27 July 2026 in Pecatu.
  • Key point: the final route is about 12 km, with a 24-metre road body and 3-metre sidewalks on each side.
  • Key point: the programme budget exceeds Rp2.9 trillion, mostly a regional loan from PT SMI; Badung targets completion of the JLS by the end of 2027.
  • Key point: we found no official study measuring the effect on property values, so treat any price promise as opinion.
  • Key point: buyers should check where a property sits relative to the alignment, plus title, zoning and permits.

Short Answer

The South Ring Road is a new road network that Badung began building in Pecatu on 27 July 2026 to ease congestion in South Kuta. Badung's completion target is the end of 2027 (detikBali). No official study yet measures its effect on property values.

What Is the South Ring Road (JLS)?

The JLS is a road network built by the Badung Regency Government to ease congestion in South Kuta, the district covering Uluwatu, Pecatu and Jimbaran. Its Segment 4, running from Labuan Sait to Pedati in Pecatu, is more than 10 km long and links Jimbaran to Uluwatu (detikBali). At the groundbreaking, Regent I Wayan Adi Arnawa warned that without new road access, Badung's tourism would become a thing of the past, and named three congestion points: Simpang Udayana, GWK and Pecatu.

Official Badung route map of the South Ring Road (JLS) from Uluwatu to Jimbaran and Simpang Siligita
The South Ring Road route in pink, existing roads in green. Source: Badung Regency Government route map (Google Earth imagery).

Key Facts at a Glance

  • Groundbreaking: Monday 27 July 2026 in Pecatu, led by Governor Wayan Koster and the Regent, at JLS Segment 4 (Labuan Sait to Pedati) and the Pura Kulat to Labuan Sait alignment (Badung Regency official site).
  • Final route: about 12 km, from the Pecatu Suluban area to Jalan Raya Karang Mas Sejahtera in Jimbaran (Antara, 22 January 2026).
  • Design: a 24-metre road body with 3-metre sidewalks on each side (detikBali).
  • Budget: more than Rp2.9 trillion for the whole programme, from land acquisition through initial construction: a Rp2.4 trillion regional loan from PT SMI and Rp511 billion of Badung's own revenue (detikBali).
  • Same package: the Berawa to Teuku Umar Barat shortcut in north Badung, 4.7 km and 10 m wide, targeted for December 2026 (detikBali).
  • Completion target for the JLS: end of 2027 (detikBali).

Route and Phases

Two figures appear in official communication, and they measure different things. In January 2026 Badung described the final Pecatu to Jimbaran route as about 12 km, from Pecatu Suluban to Jalan Raya Karang Mas Sejahtera, after owners of land on the three remaining alignments signed their agreement (Antara; Badung Regency). At the July 2026 launch, the Regent said the first phase, 2026 to 2027, covers the Jalan Lingkar Selatan and the redesign of Simpang Siligita, 10.89 km in total, plus the 4.77 km Semer to Teuku Umar Barat road (Badung Regency official site). Sections under construction include Uluwatu Temple, Pura Kulat, Labuan Sait and Pedati.

Aerial view of the South Ring Road corridor cleared through the Bukit Peninsula, with houses on both sides and the existing main road on the right
Road works on the South Ring Road corridor, seen from a drone on 6 October 2026. Photo: Uluwatu Property.

Several supporting works were announced at the same time (detikBali):

  • The existing Pecatu to Melasti road widened from 6 m to 10 m.
  • Simpang Siligita widened toward Denpasar, with new traffic lights.
  • A Simpang Wanagiri to Unud road (one-way toward RS Unud), with land freed in 2026 and operation targeted for 2027.
  • A one-way system at Goa Gong once the Unud to GWK to Goa Gong alignment is built.

The project has a long history. Earlier on, residents filed a civil suit against Badung's public works office over land compensation and asked for construction to stop (Antara).

A Separate Change: Traffic Flow on Jalan Raya Uluwatu

Separately from the ring road, Pecatu village introduced a new traffic flow system on Jalan Raya Uluwatu from 2 June 2026 (The Bali Sun, secondary). It is a short-term measure, not a replacement for new road capacity.

What Could It Mean for Property in Uluwatu and Pecatu?

Better access is one of several factors buyers weigh on the Bukit, and the JLS targets exactly the junctions where traffic is worst. A faster, more predictable trip to GWK, Pecatu and Uluwatu can matter for rental guests and for owners who live on site. But be careful with promises. We have not found any official appraisal or study measuring a change in property values linked to the JLS, and an end-2027 target can slip. Location, land title, zoning, permits and rental performance still decide whether a specific property is a good investment; see Uluwatu versus Canggu for the wider market.

To see the market the road serves, look at what is for sale today. On 18 November 2026, Uluwatu Property lists 84 villas and 12 land plots in Pecatu. Of the 84 villas, 43 are priced below USD 300,000 and 24 at USD 500,000 or more. Ungasan, further along the corridor, has 114 listings of villas and land. Browse them in our Uluwatu area guide, our Ungasan listings or all properties for sale in Bali. Source: Uluwatu Property listings, 18 November 2026.

What to Check Before Buying Near the Route

  • Where the property sits relative to the confirmed segments, and whether any land is affected by the alignment.
  • Land title and zoning status, confirmed by an independent notary or legal advisor; see our due diligence guide.
  • Building permits (PBG) and compliance with local spatial planning; see our permits guide.
  • Realistic rental assumptions that do not rely on future road improvements.

FAQ

Is the South Ring Road finished?

No. Construction began on 27 July 2026, and Badung's target for the JLS is the end of 2027.

How long is the South Ring Road?

Badung describes the final Pecatu to Jimbaran route as about 12 km, and the first construction phase as 10.89 km including the Simpang Siligita works.

Where was the groundbreaking?

At Labuan Sait and Jalan Pedati in Pecatu village, Uluwatu.

Will it raise property prices?

Nobody can give a number yet: no official study measures the effect. On paper, better access should support demand, and our view at Uluwatu Property is that prices in the corridor are likely to rise over time. That is our opinion, not a sourced forecast, and it depends on the works finishing on schedule.

Who is paying for it?

The Badung Regency Government, with a Rp2.4 trillion PT SMI loan and Rp511 billion of regional revenue.

Conclusion

The South Ring Road is a real, funded project that has started, aimed at the worst bottlenecks on the Bukit. Its benefit for property is plausible but unmeasured, and the end-2027 date can slip. Buy on title, zoning, permits and realistic rental numbers, not on the road alone.

Sources

Checked on 19 November 2026.

Not independently verified: construction progress after 27 July 2026, the end-2027 completion date, any effect on property values, and our own listing counts and price tiers (Uluwatu Property data, 18 November 2026).

Where to Start

Looking at Uluwatu or Pecatu? Tell us your budget and goals and we will check the property against the route, title and permits. Contact us.

Contact us for more information

whatsapp number
Invalid Number!
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
Bart
Bart
Founder & Managing Director of Uluwatu Property

Founder of Uluwatu Property, Bart brings 12 years of property expertise and strong local market knowledge. Speaking French and English, he helps clients navigate Bali's property market and identify the right investment opportunities.

Ready to invest in Bali?
Let's find your place in Uluwatu
Contact us today
Contact us today